How to Read a Pump Curve and Find the Duty Point

Read flow and head as a pair, then check where the pump and system curves meet. Maximum figures alone do not tell you how much water your installation will deliver.

Conceptual illustration of a descending blue line and rising orange line meeting at a marked point on unnumbered axes

A pump advertised with a high maximum flow and a high maximum head may still miss the combination you need. Those two figures normally describe different operating conditions. What matters is how much head the pump can provide at your required flow.

Start with a pair such as 3 m³/h at 60 m total dynamic head (TDH). Find that flow on the horizontal axis, move up to the correct pump curve, then read the head on the vertical axis. That is the first comparison. To predict the actual flow in the installation, you also need the system requirements and the pump’s operating limits.

This guide covers centrifugal pumps, including multistage borehole pumps. If you do not yet have the required flow and TDH, start with the borehole pump sizing guide and the TDH calculation examples. A borehole’s total depth alone is not the head to plot.

First, make sure you have the right curve

Before tracing any lines, read the model and conditions printed on the sheet. Similar-looking pumps, or pumps with the same kW rating, can have different curves.

  • Match the exact model and hydraulic version. For a multistage borehole pump, check the stage count; for a pump offered with different impeller diameters, identify the applicable diameter.
  • Match the stated speed and frequency. A curve for a different speed does not establish your pump’s performance. With a variable-speed drive, ask which operating speed the proposed selection uses.
  • Check both axes. Flow may be in m³/h, L/min or gallons per minute; head may be in metres or feet. Identify US or Imperial gallons where relevant. 3 m³/h = 50 L/min.
  • Read the liquid and test conditions. Do not transfer a clean-water curve unchanged to a different liquid without checking its applicability.

A family chart may show several models or speeds on one sheet. Follow one identified curve throughout the comparison. The Hydraulic Institute’s guide to pump curves explains the different performance lines and the importance of their stated conditions.

If all you have is a photograph of the nameplate or a short quotation, that is enough to start a document request. Ask for the complete performance sheet for that exact configuration. You do not need to reconstruct a curve from the model name.

A real catalogue example: keep each flow with its head

The QDD catalogue row for 100QJ6-40/9 gives three flow–head pairs:

  • At 4 m³/h, the listed head is 56 m.
  • At 6 m³/h, the listed head is 40 m.
  • At 7 m³/h, the listed head is 24 m.

The 100QJ series page displays the central reference point, 6 m³/h at 40 m. The other catalogue values show why it would be wrong to combine 7 m³/h with 56 m: they belong to different columns.

These are catalogue reference points for reading the table, not a selection for an unspecified site. The first and last listed points are not labelled here as maximum head or maximum flow. Three points also do not establish the full curve, efficiency, or permitted operating range. Request the complete model-specific sheet before confirming the pump.

Read one flow–head pair from the curve

The following graph is a teaching example, not a QDD model curve. At a fixed speed, its line falls from 90 m at zero flow to lower head as flow increases.

To read the example, find 3 m³/h on the bottom axis. Move vertically to the blue pump line, then horizontally left to the head axis. The answer is 60 m. The two readings describe one point: 3 m³/h at 60 m.

Teaching pump curve with guide lines linking 3 cubic metres per hour to 60 metres head, and a separate zero-flow point at 90 metres
Move up from the required flow to the pump line, then left to read head. This illustrative curve is not product data, and its displayed right endpoint is not a stated maximum flow.

Now put your required flow and TDH on the same axes. If the required point is above the pump line, the illustrated pump cannot supply that head at that flow under the stated conditions. If it is below the line, there is more pump head available at that flow than the system requires. That does not mean the pump will automatically deliver exactly the flow you marked; the operating point can move, or the design may need a different pump, speed or control arrangement.

At zero flow, the head is called the shut-off head. On the usual falling Q–H curve, this is the highest head. A maximum-flow figure refers to a different, low-head condition. Neither figure promises useful water delivery at the other maximum. Also, the right edge of a published curve may simply be where the manufacturer stops its data: do not extend it to zero head and call the result a usable maximum flow.

The actual operating point is where pump and system agree

Your required duty point describes what the installation needs. The operating point describes where it actually runs. They match only when the selected pump, system and controls make them match.

For a fixed pump speed and fixed system configuration, plot the complete system head requirement against flow. The pump and system curves meet at a point where both give the same head at the same flow. KSB’s explanation of the operating point describes this intersection.

Here is a small numerical example you can check. It is independent of the earlier catalogue model and uses a simplified system with a fixed water level. Q is in m³/h and all head values are in metres:

Pump head = 90 − (10/3) × Q²

System head = 45 + (5/3) × Q²

The 45 m term represents the fixed elevation and pressure requirement. The second term represents a simplified flow-dependent contribution. At Q = 3, the pump provides 90 − 30 = 60 m, and the system needs 45 + 15 = 60 m. Point A is therefore 3 m³/h at 60 m.

These equations were chosen to make the example readable. They are not measured performance or a borehole-loss model. Real system calculations use the actual route, components and source conditions. If you arrived here from the TDH article, note that this example uses a different system breakdown, even though the initial 3 m³/h at 60 m result is the same.

One pump curve intersects system A at 3 cubic metres per hour and 60 metres, and the higher system B at about 2.65 cubic metres per hour and 66.7 metres
A and B use the same fixed-speed teaching pump. Increasing the fixed system head by 10 m moves the intersection to lower flow; the equations and fixed-water-level assumptions are explained in the text.

What changes when the water level falls?

Keep the teaching pump at the same speed and increase the system’s fixed head requirement from 45 m to 55 m. This represents a source level 10 m lower, with the delivery conditions and flow-dependent coefficient unchanged. The new system line is:

System head = 55 + (5/3) × Q²

At the original 3 m³/h, the system now requires 70 m, but the pump still provides only 60 m at that flow. It cannot keep the old flow under these assumptions.

The new intersection satisfies 90 − (10/3) × Q² = 55 + (5/3) × Q², so Q² = 7. Point B is approximately 2.65 m³/h at 66.7 m. Flow has fallen from 50 to about 44 L/min. The 70 m figure is the requirement at the old flow; it is not the new operating head.

For a real borehole, pumping water level can itself change with flow, time and season. The two fixed water levels above isolate one effect; they do not predict the response of every well. Use pumping-test information and the expected water-level range when checking the actual selection.

Likewise, a different pipe route or valve position changes the system requirement, while a different speed changes the pump curve. Active pressure or flow control must be considered in its operating state. The Hydraulic Institute’s combined-curve examples show why these changes affect the intersection. More available flow is only useful if the well can sustain it and the equipment remains within its limits.

A point on the line is not yet an approved selection

Once the candidate can meet the required flow and head, check how it will operate across the expected range—not just at one convenient water level.

Find the actual efficiency information. The best efficiency point (BEP) is the peak of the relevant pump efficiency curve. It cannot be identified from the middle of a Q–H line or from its shape alone. A stated pump efficiency is also not automatically the efficiency of the pump, motor and drive together.

Ask for the permitted operating range. The preferred operating region (POR) is the preferred range around BEP. The allowable operating region (AOR) is the wider range permitted under the manufacturer’s specified conditions. Use the applicable limits; do not adopt a universal percentage around BEP as permission to run any pump there. The Hydraulic Institute’s operating-region explanation describes the distinction.

Read the power definition. A kW line may describe shaft power required by the pump rather than electrical power drawn from the supply. Confirm its meaning and check the motor and drive over the expected operating range. A lower head does not, by itself, prove that motor loading will fall.

Keep the installation limits in the decision. For a borehole pump, confirm sustainable well output, required submergence, motor cooling and any limits on starts or speed. Where NPSH data applies, the available NPSH must satisfy the manufacturer’s requirement and margin. A Q–H match alone does not confirm these conditions.

Ask for a marked curve, not just a larger motor

For an initial enquiry, send the curve or model information you already have and state the job in one line: “We need 3 m³/h at approximately 60 m TDH for tank filling.” Add the available power supply and any known change in pumping water level. If a value is unknown, mark it “to confirm”.

Ask the supplier to return the exact model and version, a curve with the proposed point marked, the applicable speed, and the operating limits. If the curve does not include efficiency or power data, ask for those separately rather than estimating them from the head line. The QDD pump selection enquiry can start with the information you already have.

A useful reply should explain what happens at both the usual and demanding conditions, including whether the required delivery flow is still available. At commissioning, have the installed flow, relevant water level and delivery conditions checked against the agreed requirement. That connects the paper selection to the water supply you actually wanted.

Keep exploring

← All pump guides

Series appearance reference. Dimensions, model versions and included accessories are confirmed in the quotation.