Set the pump intake below the lowest expected pumping water level with the water cover required by the selected pump. Leave room below the complete pump and motor assembly for the clearance the well and equipment need. Then check the proposed position against the well’s water entry zones, motor cooling and equipment limits.
Start with the borehole completion record and a pumping test. If you have an older well, ask for its current usable depth as well. The completion record helps locate the casing and water entry zones before the installer checks a proposed setting. GEOSS guidance on borehole records.
Measure every depth from the same point
Use one marked point, such as the top of the well casing, and record all depths down from that point. A water reading taken from the casing and a pump depth quoted from ground level need to be put on the same basis before you compare them.
- Static water level is the depth to water after the well has recovered with the pump off.
- Pumping water level is the depth to water during pumping. Record the flow and elapsed pumping time with it. Use the test and site records to assess the lowest water level expected at the intended flow, including seasonal changes.
- Pump setting needs a named reference on the assembly. Ask whether the quoted depth is to the outlet, intake or bottom of the motor. Record the offsets on the selected assembly.
- Usable bottom is the currently verified depth available in the well. Compare it with the original drilled depth if sediment or an obstruction may have reduced the space.
Use the pumping water level to work out the lift from the water surface to the delivery point. The pump setting serves a different purpose. It locates the equipment and helps define the length of pipe and cable, along with the installation checks. QDD’s guide to total dynamic head.
Find a setting range, then check the well and equipment
Find the shallowest intake position. Add the selected pump’s required water cover above the intake to the depth of the lowest expected pumping water level. This water cover is the intake submergence. If the manual calls for the whole pump to be submerged or uses a different reference point, use the assembly dimensions to express that requirement as an intake depth. A test at a different flow or at a wetter time of year may give a different water level. Grundfos SQ/SQE installation instructions.
Find the deepest position allowed by the bottom. Start with the verified usable bottom. Subtract the required gap between the bottom and the lowest part of the assembly. Then subtract the distance from the intake to that lowest part. This gives the deepest intake position allowed by the bottom clearance. Use the well log, current condition and selected equipment to agree the clearance.
Check where water enters the well. Use the screen or open-hole water entry zones and the motor instructions to check that water will flow past the motor over the intended operating range. Water entering above the motor can reach the intake without providing enough cooling along the motor. A wide bore or low flow can also affect cooling. The equipment instructions determine whether a flow sleeve is needed and how it should direct the water. Franklin Electric’s guidance on motor cooling and flow sleeves.
Check maximum submergence separately. Compare the model’s permitted depth below water with the highest water level expected around the installed assembly. Use the equipment manufacturer’s measurement point for that limit. As water rises, the installed unit sits farther below the water surface. Also confirm passage through the casing, connections, cable and support for the proposed setting. QDD’s borehole installation accessories.
Worked example with one well datum
Suppose a borehole was drilled to 60 m and its current usable bottom is 56 m. The recovered static water level is 14 m. A test at the design flow of 2 m³/h records a pumping water level of 36 m. For this example, the installer uses 41 m as the lowest expected pumping water level at that flow.
Assume the chosen equipment requires at least 4 m of water above the intake and the well assessment calls for a 5 m gap from the bottom of the assembly to the usable bottom. The bottom of the assembly is 1.2 m below the intake. These are example inputs for the calculation.
| Geometric check | Result |
|---|---|
| Shallowest intake | 41 + 4 = 45 m |
| Deepest intake allowed by the bottom | 56 − 5 − 1.2 = 49.8 m |
| Intake range from these two checks | 45 to 49.8 m |

At an intake depth of 47 m, the bottom of the assembly is at 48.2 m. The intake has 6 m of water cover at the low pumping level, and the assembly has 7.8 m of clearance above the usable bottom. This position passes the two geometric checks. The screen or water entry zones, cooling and other equipment limits determine whether the setting can be used.
If the expected pumping water level drops to 47 m at the same flow, the intake would need to be at least 51 m deep under the example requirements. The bottom check still allows only 49.8 m. With no overlap, ask the installer to reassess the flow, the well or the equipment and repeat the checks for the revised arrangement.
Record the setting before and after installation
Give the installer the well log, the depth datum, the current usable bottom, the water levels and the flow and time from the pumping test. Add the required delivery flow and the intended destination. If a measurement is missing, identify it as an item to verify on site.
Ask for the final intake and assembly depths, the model and cooling arrangement, and the conditions used for approval. During commissioning, record the pumping water level at the operating flow and verify the low-water protection where fitted. These readings give you a baseline for checking the installation when water levels or demand change. QDD’s borehole pump installation and commissioning checklist.