Choose submersible pump cable from the exact motor’s electrical requirements, the complete cable route and the installation conditions. Check both current-carrying capacity and voltage drop, using the applicable motor or drive instructions. A pump’s HP rating or borehole depth alone cannot specify the cable cross-section.
If you are preparing an enquiry, start with the motor model or nameplate photo, the supply and starting method, and the route lengths you already know. Existing cable markings and installation records help. Missing measurements can be completed with the installer; you do not need to open electrical equipment or lift the pump to start the discussion.
Record the motor and starting method first
Collect the rated voltage, phase, frequency and current, together with the full motor model. Check what the power marking describes instead of treating shaft kW as the electrical input. The cable selection must correspond to the actual motor and operating arrangement.
Identify whether the motor uses direct-on-line starting, a specific single-phase control box, another starter or a variable-frequency drive. Use the appropriate instructions for that arrangement. A cable chart for one voltage, phase or motor family cannot be transferred to another simply because the HP is the same.
Also confirm the required working conductors and protective earth. Motor descriptions such as “two-wire” and “three-wire” do not necessarily include the protective-earth conductor in that count. For example, Cerrowire’s submersible cable range lists working conductors and ground separately. This is a naming example, not a rule for every motor or a local wiring-colour instruction.
Ask for conductor cross-section in the units used by the chosen table, such as mm² or AWG, plus conductor material and the required core arrangement. Overall jacket thickness does not reveal the conductor cross-section.
Count the complete route before reading a cable chart
Locate the table’s starting point and endpoint. The Franklin Electric 50 Hz AIM manual, for example, labels its relevant tables “Service Entrance to Motor.” Counting only from the control box or borehole head would omit part of that specified route.
For a simple illustration, assume a direct-on-line installation with no drive and these route lengths:
- From the table-defined supply start to the wellhead: 35 m along the actual cable route.
- From the wellhead to the motor: 85 m of downhole route.
- Additional cable actually installed for routing and terminations, not already counted above: 5 m.
The one-way physical route is 35 + 85 + 5 = 125 m. The 85 m is the route to the motor, not the total drilled depth or the depth to the water surface. The extra 5 m is an assumption for this example, not a standard allowance for every installation.

Include bends, changes of level and the actual path across the site. Identify how the motor lead and joints are included in the selected manufacturer’s length convention. Avoid adding the same lead or allowance twice. Spare cable left on a stock reel is different from cable that remains in the installed circuit.
One-way length and circuit length are different conventions
If a manufacturer’s chart already asks for the one-way route from supply to motor, do not automatically double 125 m before looking it up. A voltage-drop formula may handle the outgoing and return conductors, or the three-phase relationship, through its own length definition and factors.
Follow the convention of the particular table or formula. Keep metres and feet consistent, and check what a published mV/A/m factor includes before adding another multiplier. Mixing the route length from one method with factors from another can produce a misleading answer.
Read the matching table and keep its assumptions
A maximum-length chart is useful when its conditions match the job. Before accepting a cable size, check:
- The motor entry: correct voltage, phase, frequency, motor family and applicable current or power row.
- The conductor entry: correct material and cross-section, with the units kept consistent.
- The route: the full length between the table’s stated endpoints, including the relevant existing feeder.
- The notes: the table’s voltage assumptions, temperature and installation conditions, starting arrangement and other limits.
In the applicable motor row, identify a cable size whose listed maximum length covers the complete route, then retain that candidate for the remaining installation and current-capacity checks.
Record the chosen table reference and the actual length alongside the permitted length for the proposed cable. This makes the selection reviewable when a motor, route or supply arrangement changes.
Current-carrying capacity and voltage drop are separate checks. The first concerns heating under the actual installation conditions. The second concerns the voltage available to the motor. Starting performance and the upstream supply also need attention; a satisfactory running-length comparison does not establish every part of the design.
Do not treat a generic percentage found online as the acceptance limit for all motors and sites. Use the applicable equipment requirements and installation rules, including how the voltage-drop allowance is shared along the supply route.
Existing feeders and mixed cable sizes share the route
A larger downhole cable does not erase voltage drop in an existing surface feeder. Likewise, checking two sections independently against the full allowance can spend the same voltage-drop budget twice.
Franklin’s manual illustrates a method for two cable sizes: divide each section’s actual length by the maximum length for that size in the same applicable motor table, then add the fractions. A sum no greater than one meets that method’s length-budget check. It still leaves current capacity, protection and installation suitability to be confirmed. Use the selected manufacturer’s method for the actual sections instead of averaging their cross-sections.
Match the cable construction to its whole environment
The same mm² marking can appear on cables with different insulation, sheaths, temperature ratings and intended service. Check the exact cable product’s suitability for the submerged section, the surface route, water conditions and required mechanical protection.
Alvern’s Power & Control Cables data illustrates why the product sheet matters: its submersible cable families have their own construction details and phase-specific voltage-drop data. The conditions attached to a current-rating column matter too; a rating for one installation arrangement does not establish capacity in every conduit, trench or grouped run.

Include the sections exposed to air, heat, conduit or grouping when assessing the installation. A submerged portion does not make the entire route water-cooled. Confirm protective-earth requirements separately, along with compatibility between the cable, motor lead, splice kit, glands and terminals.
The joint and mechanical installation matter as much as the cable marking. Follow the applicable instructions for sealing, strain relief, support and protection from abrasion. The electrical cable must not carry the pump or rising-main weight.
A drive-fed motor needs its own cable-length check
For a variable-frequency drive, separate the supply cable feeding the drive from the motor cable leaving it. They are different electrical sections. Do not add both into a direct-on-line motor chart and assume the result sizes the drive system.
The drive, motor and any output filter can impose motor-cable length, construction, earthing or shielding requirements. Long output cables involve more than ordinary running-voltage drop. Increasing conductor area alone does not establish that a filter or a different arrangement is unnecessary.
Grundfos’s frequency-drive lesson explains output filtering and the distinction between cable sections in its example. Obtain the requirements for the actual drive and motor, including the proposed filter configuration. For a solar pumping drive, keep PV input wiring data separate from motor-output cable selection.
Give the installer a complete cable brief
For a first enquiry, send the available motor and controller information, approximate surface and downhole lengths, and any existing cable records. Have the installer identify missing measurements and electrical checks. State whether the work concerns a new installation, a longer route or the reuse of an existing feeder.
| Selection input | What to provide |
|---|---|
| Motor identity | Full model, voltage, phase, frequency, rated current and available nameplate information |
| Supply and controls | Supply arrangement, starter/control-box or drive model, and output filter if used |
| Route sections | Each section’s start, end and actual length, with motor lead and installed allowances identified |
| Existing cable | Product markings, conductor material, cross-section and core arrangement where known |
| Installation conditions | Submerged and surface sections, temperature exposure, conduit, burial, grouping and mechanical protection |
| Connections and protection | Motor-lead/splice compatibility, glands, terminals and protective-earth requirements |
| Selection evidence | Applicable manufacturer table or calculation, its assumptions and the checks still outstanding |
Before lowering the pump, record the cable and joint details that will become inaccessible. Have the installer complete the applicable continuity, insulation, earthing, protection and operating checks in accordance with the equipment instructions. Testing must account for connected electronic controls; a generic test procedure is not suitable for every drive and motor.
At handover, retain the installed lengths and sizes, the selection basis, and the operating readings used to confirm satisfactory motor supply and starting. Check normal water delivery under the intended operating conditions as well. QDD’s submersible cables and splice kits page is a starting point for discussing the required cable and connection specification.