Borehole Pump Installation and Commissioning Checklist

Prepare for borehole pump installation and commissioning with practical checks, a copyable first-run record and clear handover criteria for equipment, controls and operating results.

Technician records observations beside a borehole wellhead with a pressure gauge, inline water meter and supported delivery pipe

A borehole pump installation is ready for handover when the equipment is correctly installed, the measured water delivery and electrical operation meet the agreed requirements, the controls work as intended, and the results are recorded. Water appearing at the outlet is only the first observation.

Use this checklist to agree what the installer will verify before lowering the pump, before energising it and during the first supervised run. It also provides a commissioning record you can copy. The exact pump, motor and control manuals determine the settings and test limits; electrical work, lifting and live measurements belong to suitably qualified personnel.

1. Agree the installation requirements and responsibilities

Before equipment arrives, assemble the borehole report, yield-test recommendations, proposed duty point and equipment documents. The duty point is the required flow at the required total dynamic head (TDH), not the pump’s maximum flow or maximum head. If these inputs are incomplete, use the borehole pump sizing guide to prepare them before installation.

Confirm who supplies the pump, motor, cable, pipework, controls and sensors, and who performs the mechanical installation, electrical verification and commissioning. Also identify who will arrange water-quality testing or treatment if the water is intended for drinking. Our quotation comparison guide helps distinguish supplied equipment from site work.

Write down the acceptance criteria before the first start: intended flow and delivery conditions, the approved pumping schedule, equipment limits and the control functions to demonstrate. Record the source of each limit, such as the exact motor manual or approved system design.

2. Check and document the equipment before lowering

Use pass, hold or not applicable against each check. “Hold” means resolve the issue before proceeding; “not applicable” needs a reason.

CheckEvidence to keep
Equipment identity and matchingPump, motor and control model numbers; nameplate photographs; serial numbers where supplied; confirmation of mechanical and electrical compatibility.
Borehole and pump positionInside diameter and unobstructed passage; planned setting depth; pumping water levels and abstraction recommendations; required submergence, bottom clearance and maximum immersion limits.
Motor coolingConfirmation that the proposed position and water path provide the motor’s required cooling. Record any required flow sleeve or shroud.
Riser and support arrangementPipe specification and length, joint and suspension details, load and pressure suitability, and the agreed lifting method.
Valves and surface pipeworkInstalled valve types, locations and direction; pressure ratings; discharge destination and provision for the required measurements.
Submersible cable and jointCable specification, conductor size and complete route length; correct joint kit; visible condition and strain protection.
Controls and sensorsExact starter or drive, protective functions, level or pressure devices, and the relevant wiring and setup documents.
Electrical baselineThe qualified person’s inspection and test results, including the applicable method and acceptance limits.

Manufacturer checklists, such as Franklin Electric’s submersible pump installation checklist, cover equipment matching, cooling, cable condition and installation checks. Use the documents for the equipment actually supplied; do not transfer another manufacturer’s numerical limits to your pump.

Confirm the position and cooling arrangement

Pump setting depth, pumping water level and total borehole depth are different measurements. Reference them to a clearly identified point, normally at the wellhead. The pump inlet must retain the submergence required by its manual under the approved operating conditions, while the assembly also meets its immersion and bottom-clearance limits.

A submerged motor still needs the specified water movement for cooling. Have the installer confirm the flow path and whether a sleeve is required. Do not use a universal “metres above the bottom” rule or assume that lowering the pump further always solves low-water operation.

Schematic showing a common wellhead depth reference, static and pumping water levels, pump inlet, pressure point and flow measurement
Use one identified depth reference and record the pressure measurement location. This schematic has no design dimensions; pump position and submergence follow the applicable manual and borehole plan.

Preserve evidence while the components are accessible

Photograph nameplates, the completed cable joint and the assembled equipment before lowering. Keep the electrical baseline with the cable length and test conditions. These records make a later change easier to investigate than a single “tested OK” statement.

Resolve any uncertain model or cable-joint condition while the equipment is still accessible.

3. Protect the assembly while lowering it

Use the approved lifting and support arrangement, keep the electrical cable protected from sharp edges and pinching, and secure it as specified for the installation. Never lower or lift the assembly by its electrical cable. The PUMPA SPP installation manual also identifies cable damage and handling as installation concerns.

Record the installed pipe and cable lengths, the final setting depth and any change from the proposed arrangement. If the assembly encounters an obstruction, stop and investigate rather than forcing it down.

Where the applicable procedure calls for electrical tests during lowering, the qualified person should compare readings with the earlier baseline. An unexpected change requires investigation before the next stage. Record the results and any corrective work, not just the final reading.

4. Hold before energising: verify the complete installation

The responsible electrical person should complete the required checks for isolation, protective earthing, supply, connections and protection before authorising energisation. Keep the inspection or compliance documentation required for the actual installation.

For insulation and winding tests, record what was tested: the motor alone, the motor with its lead, or the installed motor and cable. Test voltage, method, temperature and acceptance limits must suit that equipment. Have the qualified electrical person isolate and disconnect the motor circuit as required by the motor and drive manuals before testing. Do not apply an insulation test through connected drive electronics; the ABB ACS550 manual explains this separation for that drive.

Confirm the drive or starter configuration against the motor nameplate. A permanent magnet motor requires a compatible drive; matching only the kW rating is insufficient. Check sensor inputs, overload and low-water protection settings, permitted speed range where relevant, and automatic restart behaviour. QDD’s drives and controls range can help identify the equipment details to send for matching.

The mechanical installer should also confirm that the pump is submerged as required, the discharge route is ready, the wellhead is secure and the startup valve arrangement follows the pump manual. Do not apply one valve-opening rule to every model, and do not run a submersible pump dry on a workbench to “see if it works”.

Keep the installation on hold if there is damaged insulation, unresolved matching, an unapproved test result, missing protective arrangements or no acceptable discharge path.

5. Make the first start a supervised measurement

Start in accordance with the equipment’s procedure. For a three-phase installation, have the qualified person verify rotation by the manufacturer’s approved method before accepting performance. A running motor with poor delivery is not proof of correct rotation. Isolate the system before any connection changes.

During the run, observe the actual water delivery, pumping water level, electrical readings, leaks, noise, vibration and control indications. Stop for unsafe electrical behaviour, loss of required submergence, unacceptable current, severe vibration, leakage or other conditions outside the approved limits. Record a fault before resetting it; repeated restarts do not establish that the problem has cleared.

Record flow, pressure and water level together

Measure and record the static water level before starting, with the time and reference point. During the run, a useful commissioning record describes one operating condition at a known time. Pair the measured flow with the pumping water level and delivery pressure, and record the valve position or control setpoint. Note where pressure was measured. A wellhead gauge reading alone is not the pump’s TDH.

Repeat readings at the agreed intervals so the installer can assess the trend. If the water level continues falling beyond the agreed trend or limits at the intended flow, investigate the abstraction rate and operating plan before accepting routine operation. Do not treat a brief successful run as a new sustainable-yield assessment.

Use a suitable flow measurement. For a small, safely accessible discharge, a timed known volume can provide a check: flow in L/min = collected litres × 60 ÷ elapsed seconds. For example, 20 litres collected in 30 seconds is 40 L/min, or 2.4 m³/h. This is a measurement example, not a recommended flow for a particular borehole. Use an appropriate meter where timed collection is unsuitable.

Copy this first-run record

Keep a separate line for each timed observation. Attach the electrical test sheet rather than compressing all results into a single tick.

Record fieldEntry
Site and equipmentSite ID: ____; date: ____; installer: ____; pump/motor/control models and serials: ____.
Installation referenceDepth reference point: ____; pump setting depth: ____ m; inlet location: ____; installed cable and pipe details: ____.
Before startingStatic water level below reference: ____ m; measurement time: ____; recent pumping or recovery conditions: ____.
Intended operationRequired flow: ____ m³/h; TDH: ____ m; delivery condition: ____; approved pumping schedule: ____.
Timed hydraulic readingTime since start: ____ min; flow: ____; pumping water level below reference: ____ m; pressure and gauge location: ____; valve/setpoint: ____.
Electrical readingSupply source and measurement location: ____; running voltage/current by phase as applicable: ____; drive output frequency where relevant: ____; measured by: ____.
Observations and limitsWater appearance, leaks, noise/vibration and fault indications: ____; applicable limit and document reference: ____; result: pass / hold.
After stoppingStop behaviour: ____; recovery water levels and times if required by the test plan: ____; restart delay or restriction: ____.

The borehole installation record, Form 2207, in the Franklin Electric 50 Hz AIM manual is another example of documenting water levels, pump position, delivery and electrical readings. Your final record should match the actual system and commissioning plan.

6. Demonstrate the controls before handover

Prove the functions the system is intended to provide. A power light or a successful manual start does not demonstrate automatic control or protection.

  • Tank filling: Demonstrate the stop at the intended high level and the restart request at the intended low level. Record the sensor positions and switching behaviour.
  • Pressure operation: Confirm the intended pressure-control response and observe stopping and restarting under the agreed demand conditions. Record the setpoints and any pressure-tank setup required by its manual. Note run/stop times and frequent cycling, and check permitted starts and restart intervals against the actual motor and control manuals.
  • Low-water protection: Use the controller manufacturer’s approved test or simulation method. Record detection, shutdown and permitted recovery/restart behaviour. Do not deliberately run the pump dry to prove the protection.
  • Normal shutdown and restoration: Confirm the accessible stop/isolation arrangements and the expected response when supply returns. Ensure the operator knows whether the system can restart automatically.

Use equipment-specific procedures for these demonstrations. Restore normal settings and all protective functions after testing, and record any function that remains unverified. Keep the installation on hold if a required safety function remains unverified.

Five stages from pre-lowering checks to documented handover, with a hold branch for failed or unverified required checks
Advance when the required checks pass. Resolve failed or unverified checks and repeat the relevant stage before release.

7. Hand over a usable operating baseline

Give the operator a concise pack containing the as-installed equipment list, nameplate photographs, depth reference and setting, pipe/cable details, system sketch, electrical test results, timed running readings, final settings and demonstrated control functions. Add the manuals, warranty/support contact and the approved operating schedule.

Separate unresolved items from passed checks. Give each item an owner and a required action. If an unresolved item affects safe operation or the agreed performance, keep handover on hold; a signature should not hide it.

Show the operator how to read the normal indications, stop the system and report a fault. State which changes need technical support. The baseline then gives future service personnel something useful to compare with when flow drops, trips occur or operating conditions change.

For an equipment or compatibility enquiry, send QDD the pump and motor nameplates, control model and recorded operating details. Where installation components need confirmation, include the actual specifications from the installation accessories list.

Common commissioning questions

How long should the first test run last?

Use the duration and observation intervals in the applicable manuals, commissioning plan and borehole recommendations. Acceptance depends on the readings, trends and completed checks, not simply reaching a universal number of minutes. A longer run cannot make an out-of-limit condition acceptable.

Does clear water mean the installation is ready for drinking-water use?

No. Appearance does not establish drinking-water quality. The US EPA guide to household wells explains that serious contamination may require laboratory testing to detect. Arrange sampling, treatment and hygiene measures appropriate to the intended use and local requirements; accepting the pump installation does not certify the water as drinkable.