Compare permanent magnet and conventional AC borehole pumps by the kilowatt-hours they use to deliver a cubic metre of water at the required duty. Ask each supplier for the electrical input at the same flow and total dynamic head. For an installed system, measure electricity on the supply side of the pump controls and divide it by the water delivered during the same period.
Start with the same water delivery task
Here, conventional AC refers to a borehole pump with an induction motor. A permanent magnet motor describes the motor design. A pump with a permanent magnet motor can also take AC mains power through its drive. Ask which motor, pump end and controller are included in each quote. The drive can be built into the pump or supplied separately. Grundfos SQ product documentation.
A permanent magnet motor uses magnets to provide the rotor’s magnetic field. This can reduce motor losses at a given shaft load. The input for the whole package also depends on the pump’s hydraulic efficiency and the drive’s efficiency at that duty. Franklin Water motor comparison. US Department of Energy drive efficiency guidance.
Give both suppliers the same flow and total dynamic head (TDH), including lift from the pumping water level, delivery pressure and pipe losses. A pump that moves less water may draw less power while taking longer to fill the tank. Confirm that each pump meets the required flow and head together on its curve. QDD guide to pump curves.
For a tank fill, specify the target volume and the time allowed to deliver it. For pressure controlled supply, give the required pressure and representative demand periods. These details let a supplier account for how the pump will run across the day.
Include the drive in the electrical measurement
Ask for active electrical input in kW at the supply side of the complete pump package. Include the drive or controller supplied with each pump and the power consumed by the equipment downstream of that measurement point. Confirm what a power column on the data sheet represents. A rated motor shaft output in kW describes mechanical output. The supply side input includes the electrical losses between the supply and that shaft. Grundfos guide to pump input and output power.
For a field comparison, have the installer obtain active energy readings in kWh and delivered volume readings in m³ over the same test interval. Use a dedicated pump supply reading and meter the water at the same delivery point for both setups. Record flow, pumping water level and delivery pressure during the test so you can see whether the two systems performed comparable work. US Department of Energy pumping system efficiency guide.
Compare kWh per cubic metre
Suppose both pumps deliver 3 m³/h at 60 m TDH and each delivers 30 m³ in ten hours. Assume steady supply side inputs of 1.10 kW for the permanent magnet option and 1.25 kW for the induction motor option. These inputs are illustrative. The example covers steady pumping.
| Comparison item | Result for the same 30 m³ delivery |
|---|---|
| Permanent magnet option, 1.10 kW | 11.0 kWh in 10 hours, or 0.367 kWh/m³ |
| Induction motor option, 1.25 kW | 12.5 kWh in 10 hours, or 0.417 kWh/m³ |

Multiply steady input power by operating hours to get kWh. Then divide by the delivered cubic metres. The 1.5 kWh difference per 30 m³ follows from the assumed inputs. For an actual purchase, repeat the calculation with comparable data for the two quoted packages. QDD guide to borehole pump power consumption.
Compare a full operating cycle when demand varies
With variable demand, use total metered kWh divided by total delivered m³ for an equivalent period. A pressure controlled system may run at several speeds and spend time waiting for demand. A tank system may run at one duty and stop between fills. Include the starts and standby energy within the agreed period for both packages. For a tank comparison, match the starting and ending water levels so that water drawn from storage does not skew the result.
If you have data for several demand periods, add the kWh and add the volumes before dividing. This gives each period the right weight. Ask for input data near the flow and pressure you expect to use most often. Motor design, pump selection and the controls all affect the energy needed for the same water delivery. US Department of Energy pump system guidance.
Ask for these figures on both quotes
| What to request | What to match |
|---|---|
| Pump, motor and controller models | The complete package offered, including the drive where used |
| Flow and total dynamic head | The same duty point, or the same set of demand conditions |
| Supply side input in kW | The same electrical measurement point with controls included |
| Energy used and water delivered | kWh and m³ over the same duty cycle or test interval |
| Data source | Published input curve, supplier test data or an installed system measurement |
QDD offers conventional AC and permanent magnet borehole pump ranges. The published series pages help narrow the selection by flow and head. For an energy comparison, send your required duty, pumping water level and operating schedule, then ask for the available supply side input data for the specific packages. QDD borehole pump ranges. QDD pump selection help.